SCHEDULE
INITIATION
- Establish Goals and Objectives
- Launch Project Website
- Establish a Planning Advisory Committee (PAC)
INITIATION MEETINGS
- PAC Meeting #1
PHASE 1
- Inventory of Existing Conditions
- Environmental Inventory
- Aviation Forecasts
- Draft Phase One Working Papers
PHASE 1 MEETINGS
- PAC Meeting #2
- Public Information Workshop #1
PHASE 2
- Facility Requirements
- Airside/Landside Alternatives
- Draft Phase Two Working Papers
PHASE 2 MEETINGS
- PAC Meeting #3
- Public Information Workshop #2
PHASE 3
- Recommended Development Concept
- Environmental Overview
- Capital Improvement Program
- Draft Phase Three Working Papers
PHASE 3 MEETINGS
- PAC Meeting #4
- Public Information Workshop #3
APPROVALS
- Draft Final Master Plan and Airport Layout Plan drawing set
- Local Approval of the Master Plan
- ALP approval by TxDOT/FAA
FINALIZATION
- Final Master Plan Report
- Deliver Digital and Printed Copies of Finalized Report
PUBLIC INVOLVEMENT
The approach to involving the community and airport stakeholders is multifaceted. Three (3) public information workshops will be held during the master planning process. These workshops, which will be conducted in an open-house format, will allow the public and airport stakeholders to participate with the airport master plan team and ask any questions they may have about the airport master plan. The workshops are typically scheduled in the early evening to accommodate those heading home from work and others who can attend after dinner. The dates and times of the workshops will be advertised locally and posted on this website.
Any interested citizen or airport stakeholder is encouraged to provide comments and suggestions to the airport master plan team. Comment sheets will be provided to the PAC and at the public information workshops.
Comments can also be submitted here.
FREQUENTLY ASKED QUESTIONS
COMMENTS
* Required Fields
Comments