GLE Terminal wide

ABOUT GAINESVILLE MUNICIPAL AIRPORT

Gainesville Municipal Airport (GLE) serves the diverse general aviation needs of North Texas, supporting business/corporate flying, recreational flying, emergency transport, and flight training. The airport encompasses more than 1,300 acres and features two runways, houses approximately 120 aircraft, and supports several on-site businesses. GLE is a significant economic contributor to the region, supporting nearly 2,300 jobs and providing more than $172 million in total economic output. Gainesville Municipal Airport is poised for continued growth and will remain a vital transportation hub for the region.

SCHEDULE

March 2025
5/13/25
Summer 2025
9/25/25
Fall 2025/Winter 2026
Tentative February 2026
Spring 2026
Tentative June 2026
Summer/Fall 2026
Fall 2026

INITIATION

  • Establish Goals and Objectives
  • Launch Project Website
  • Establish a Planning Advisory Committee (PAC)

INITIATION MEETINGS

  • PAC Meeting #1

PHASE 1

  • Inventory of Existing Conditions
  • Environmental Inventory
  • Aviation Forecasts
  • Draft Phase One Working Papers

PHASE 1 MEETINGS

  • PAC Meeting #2
  • Public Information Workshop #1

PHASE 2

  • Facility Requirements
  • Airside/Landside Alternatives
  • Draft Phase Two Working Papers

PHASE 2 MEETINGS

  • PAC Meeting #3
  • Public Information Workshop #2

PHASE 3

  • Recommended Development Concept
  • Environmental Overview
  • Capital Improvement Program
  • Draft Phase Three Working Papers

PHASE 3 MEETINGS

  • PAC Meeting #4
  • Public Information Workshop #3

APPROVALS

  • Draft Final Master Plan and Airport Layout Plan drawing set
  • Local Approval of the Master Plan 
  • ALP approval by TxDOT/FAA

FINALIZATION

  • Final Master Plan Report
  • Deliver Digital and Printed Copies of Finalized Report

PUBLIC INVOLVEMENT

IMG_0866

The approach to involving the community and airport stakeholders is multifaceted. Three (3) public information workshops will be held during the master planning process. These workshops, which will be conducted in an open-house format, will allow the public and airport stakeholders to participate with the airport master plan team and ask any questions they may have about the airport master plan. The workshops are typically scheduled in the early evening to accommodate those heading home from work and others who can attend after dinner. The dates and times of the workshops will be advertised locally and posted on this website.

Any interested citizen or airport stakeholder is encouraged to provide comments and suggestions to the airport master plan team. Comment sheets will be provided to the PAC and at the public information workshops.

Comments can also be submitted here.

FREQUENTLY ASKED QUESTIONS

COMMENTS

* Required Fields

Comments